01 · Why it mattersWhat actually decides the outcome
Every production estimate comes back to cycle time: how long one loading, hauling, placing or lifting cycle takes, and how many fit in a productive hour. Measuring the real cycle on site, rather than the brochure cycle, shows whether the machine, the operator, the layout or the interface is the constraint.
02 · Before you hireWhat to check
- Break the cycle into load, travel, dump/place and return
- Time 10–20 cycles, not one
- Record waiting separately from working
- Convert to units per productive hour
- Compare to target and identify the bottleneck
- Recheck after layout changes
03 · Supplier questionsWhat to ask the hire company
- What cycle time did you assume in the quote?
- What productive hours per shift did you assume?
- What site factors would change that assumption?
Estimating output from a single timed cycle on the best part of the day and carrying it into the programme.
04 · Put it in writingConfirm the assumptions
Record the nominated machine (make, model and configuration), the attachments, the transport method and the support arrangements in the hire agreement. If any assumption changes on site, the rate, programme or safe work method may change with it. Return it to the project team before the machine is dispatched.