418 plant & equipment hire suppliers · 15 machine classes · 56 locationsIndependent Australian hire directory

Plant productivity · PL-03

Useful utilisation

Separate available hours, operating hours and productive hours.

Useful utilisation: machinery hire guide

Separate available hours, operating hours and productive hours.

01 · Why it mattersWhat actually decides the outcome

Available hours, operating hours and productive hours are different numbers. A machine can be available for 10 hours, run for 8 and produce for 6. Separating them shows whether cost is being lost to breakdowns, waiting, poor planning or low output, and puts hire costs on a comparable basis.

02 · Before you hireWhat to check

  • Hire hours paid
  • Engine or SMU hours recorded
  • Productive hours estimated from output
  • Standby and waiting hours with causes
  • Breakdown hours with supplier response
  • Cost per productive unit, not per hire hour

03 · Supplier questionsWhat to ask the hire company

  1. Does your telematics report idle versus working hours?
  2. How is breakdown time treated in the rate?
  3. Can daily reports include hours and output?
Common mistake

Judging machines by hire rate while ignoring that one machine spent a third of its paid hours idling.

04 · Put it in writingConfirm the assumptions

Record the nominated machine (make, model and configuration), the attachments, the transport method and the support arrangements in the hire agreement. If any assumption changes on site, the rate, programme or safe work method may change with it. Return it to the project team before the machine is dispatched.