Compare machinery hire quotes on equal terms

The lowest visible rate can conceal transport, minimum hours, attachments, fuel, support and off-hire differences.

Compare machinery hire quotes on equal terms

The lowest visible rate can conceal transport, minimum hours, attachments, fuel, support and off-hire differences. Use this guide to structure the conversation with suppliers, expose assumptions early and create a record that survives the handover from estimator to site supervisor.

Step 01Normalise the inclusions

Place rate basis, minimum hire, included hours, overtime, operator, attachments, delivery, fuel and maintenance in one comparison table.

Step 02Price project interfaces

Add establishment, permits, escorts, inductions, accommodation, refuelling, standby and collection. Mark assumptions rather than hiding them in a total.

Step 03Test capability and continuity

Compare the nominated machine, operator experience, service coverage and replacement capacity alongside price. A defensible award explains the trade-off.

Record it

For each step, record the answer, where the evidence came from, who owns it and the date. If an answer changes the rate, programme or safe work method, take it back to the project team before the machine is dispatched.

ChecklistBefore you confirm the hire

  • Same rate period
  • Same attachments and operator basis
  • Mobilisation and permits
  • Standby and overtime
  • Support and replacement

ContinueRelated tools and guides

FAQQuestions before dispatch

What should be confirmed in writing with the hire supplier?

Start with the field checks for this guide (same rate period, same attachments and operator basis, mobilisation and permits and so on). Then confirm the nominated make, model, configuration, availability, transport, support arrangements and every commercial assumption in the hire agreement.

Is this guide a substitute for engineering or legal advice?

No. It is a procurement and planning framework. Engineering, legal, safety and regulatory decisions must be made by competent people for the actual project and site.

When should this information go to suppliers?

Issue the core inputs before requesting quotes so every supplier prices the same scope. Update them when site conditions change, and carry the agreed assumptions into dispatch and pre-start documents.