Field manual · FM-02
Build a specification that can actually be transported
Operating capacity is irrelevant if the nominated machine cannot reach, enter or unload at the workface.

Operating capacity is irrelevant if the nominated machine cannot reach, enter or unload at the workface. Use this guide to structure the conversation with suppliers, expose assumptions early and create a record that survives the handover from estimator to site supervisor.
Step 01Capture transport dimensions
Request mass, width, height and length in transport configuration, including attachments and counterweights. Confirm what must be removed and how reassembly will be controlled.
Step 02Prove the route
Check bridge limits, overhead services, turning paths, grades, delivery windows and permit assumptions. The last kilometre and unloading area frequently control the whole movement.
Step 03Plan demobilisation now
Define collection notice, cleaning, attachment condition, access restoration and evidence of off-hire before the machine arrives.
For each step, record the answer, where the evidence came from, who owns it and the date. If an answer changes the rate, programme or safe work method, take it back to the project team before the machine is dispatched.
ChecklistBefore you confirm the hire
- Transport mass and dimensions
- Permit and escort basis
- Last-kilometre access
- Unload and assembly method
- Collection and off-hire evidence
ContinueRelated tools and guides
FAQQuestions before dispatch
What should be confirmed in writing with the hire supplier?
Start with the field checks for this guide (transport mass and dimensions, permit and escort basis, last-kilometre access and so on). Then confirm the nominated make, model, configuration, availability, transport, support arrangements and every commercial assumption in the hire agreement.
Is this guide a substitute for engineering or legal advice?
No. It is a procurement and planning framework. Engineering, legal, safety and regulatory decisions must be made by competent people for the actual project and site.
When should this information go to suppliers?
Issue the core inputs before requesting quotes so every supplier prices the same scope. Update them when site conditions change, and carry the agreed assumptions into dispatch and pre-start documents.