Plan a controlled lift before requesting crane capacity
Crane tonnage is only the label. Radius, configuration, ground and rigging determine the real lift.

Crane tonnage is only the label. Radius, configuration, ground and rigging determine the real lift. Use this guide to structure the conversation with suppliers, expose assumptions early and create a record that survives the handover from estimator to site supervisor.
Step 01Define the load case
Confirm verified load mass, centre of gravity, pick and set radii, hook height, rigging allowance and required clearance through the complete movement.
Step 02Establish the setup
Map crane position, outrigger reactions, bearing capacity, underground services, assembly space and access for counterweights and support vehicles.
Step 03Coordinate the workfront
Align permits, lift study, rigging, communications, exclusion controls, weather limits and contingency. Availability must match the engineered configuration.
For each step, record the answer, where the evidence came from, who owns it and the date. If an answer changes the rate, programme or safe work method, take it back to the project team before the machine is dispatched.
ChecklistBefore you confirm the hire
- Verified load and centre of gravity
- Pick and set radius
- Configuration and chart
- Ground-bearing verification
- Rigging and exclusion plan
ContinueRelated tools and guides
FAQQuestions before dispatch
What should be confirmed in writing with the hire supplier?
Start with the field checks for this guide (verified load and centre of gravity, pick and set radius, configuration and chart and so on). Then confirm the nominated make, model, configuration, availability, transport, support arrangements and every commercial assumption in the hire agreement.
Is this guide a substitute for engineering or legal advice?
No. It is a procurement and planning framework. Engineering, legal, safety and regulatory decisions must be made by competent people for the actual project and site.
When should this information go to suppliers?
Issue the core inputs before requesting quotes so every supplier prices the same scope. Update them when site conditions change, and carry the agreed assumptions into dispatch and pre-start documents.